Current Construction Projects

The Village of Winnetka continues to change and improve, often with the help of public infrastructure projects. We strive to provide up-to-date information about the projects with the most impact on those living, working, and visiting the community. Please keep in mind that construction zones can be dangerous. The Village encourages everyone to heed construction signs and warnings and to ensure that children do not play on or near construction sites.

Helpful Documents

2022 Street Rehabilitation Program

The Village has awarded this year's Street Rehabilitation program to ALamp Concrete Contractors.  The project includes water main and water service replacement; pavement patching; and road resurfacing. Advanced construction notices were mailed out to the impacted residents only; additional notices will be passed out ahead of construction in affected areas. 

View the 2022 Street Rehabilitation Construction Letter

View the Gage Street and Gordon Terrace Intersection Closure Notice for street closure on Friday, July 1, 2022. 

View the Gage Street and Gordon Terrace Road Closure Notice for street closure on Friday, July 13, 2022.

View the Gage Street and Green Bay Road Closure Notice on July 27, 2022.

View the Tower Road Construction Notice from July 29, 2022.

Gage and Merrill Street 
The Contractor completed all the restoration work and final asphalt surface. The road is open to traffic and parking. 

Locust Street
During the week of September 19, the contractor completed the pavement patches and removals. During the week of September 26, the contractor will complete the concrete work and roadway milling. 

Sunview Lane
During the week of September 19, the contractor  completed the water service connections; the final connection will occur on September 23. During the week of September 26, the contractor will work on pavement patches and concrete work in preparation for the milling and resurfacing of the roadway.  

Maple Street
During the week of September 19, the contractor completed the concrete work, including sidewalk ramps and curb sections. The contractors also completed the resurfacing of the roadway. During the week of September 26, the contractor will restore the parkway and pavement striping.   

2022 Sidewalk Program

The sidewalk program for 2022 is substantially complete. During the week of August 15, the contractor removed and replaced sidewalks at various locations. 

Sanitary Manhole Rehabilitation Program

During the week of August 29, the contractor, Archon Construction, began performing the sanitary manhole rehabilitations. The manholes proposed to be rehabilitated were specifically called out as part of the 2018 inflow and infiltration study performed by the Village. This rehabilitation project includes replacing sewer manhole covers, installing internal chimney seals, and spraying cementous manhole lining. This work will give the manhole a longer life span and seal the manhole and reduce the amount of inflow and infiltration into the sanitary system. 

  1. 1
  2. 2
  3. 3
  4. 4